New: progress weighted by person-hours

You can now estimate each work package of your WBS in person-hours. yourWBS uses that estimate to calculate the progress of every parent element, so the % complete reflects the real effort and not a simple average.

The problem with a simple average

Until now, a parent element was the simple average of its children. That works when every child is roughly the same size, but real work packages rarely are. Take a phase with two deliverables:

Deliverable Estimate % complete
1.1 Requirements document 10 h 100%
1.2 System build 90 h 0%
1 Phase 100 h 50% by simple average, 10% by effort

A simple average says the phase is half done. In reality only 10 of its 100 hours of work are complete. Weighting by effort gives you the honest number.

How it works

Leaving something unestimated is fine

Not every team estimates every element, and that is a valid choice. yourWBS shows unestimated elements as a gentle warning, not as an error: a warning icon on the field, and a note on each parent saying how many deliverables still need an estimate and that its progress is a simple average for now.

Where you see it

Why effort and not dates

A WBS describes what the project delivers, not when. Scheduling tools measure progress by the duration of each task. yourWBS has no dates, so it measures progress by the work that is done. Person-hours are the natural unit for that. Read more in yourWBS vs MS Project.

Try it. Open a project, add hours to your work packages and watch the progress of each phase update. Free, no sign-up.