New: progress weighted by person-hours
You can now estimate each work package of your WBS in person-hours. yourWBS uses that estimate to calculate the progress of every parent element, so the % complete reflects the real effort and not a simple average.
The problem with a simple average
Until now, a parent element was the simple average of its children. That works when every child is roughly the same size, but real work packages rarely are. Take a phase with two deliverables:
| Deliverable | Estimate | % complete |
|---|---|---|
| 1.1 Requirements document | 10 h | 100% |
| 1.2 System build | 90 h | 0% |
| 1 Phase | 100 h | 50% by simple average, 10% by effort |
A simple average says the phase is half done. In reality only 10 of its 100 hours of work are complete. Weighting by effort gives you the honest number.
How it works
- Estimate the work packages. Enter the person-hours of each lowest-level element, in the properties panel or in its WBS dictionary sheet.
- Parents add up on their own. A parent element shows the sum of the hours of its children. You never type it, so it cannot contradict them.
- Progress is weighted by hours. When every child of a parent has an estimate, the parent's % complete is weighted by those hours.
- No estimate yet? Nothing breaks. If some children are not estimated, that parent keeps using the simple average, and yourWBS flags what is missing. The rule applies to each parent separately, so a branch you have not estimated yet does not stop the others from being weighted.
Leaving something unestimated is fine
Not every team estimates every element, and that is a valid choice. yourWBS shows unestimated elements as a gentle warning, not as an error: a warning icon on the field, and a note on each parent saying how many deliverables still need an estimate and that its progress is a simple average for now.
Where you see it
- The properties panel and the WBS dictionary sheet of each element.
- An optional Hours column in the hierarchy view, with its own switch. It is off by default, so if you do not estimate, nothing changes for you.
- The PDF of the hierarchy (when the column is on) and the PDF of the WBS dictionary.
- The project file you export and import keeps the estimates.
Why effort and not dates
A WBS describes what the project delivers, not when. Scheduling tools measure progress by the duration of each task. yourWBS has no dates, so it measures progress by the work that is done. Person-hours are the natural unit for that. Read more in yourWBS vs MS Project.
Try it. Open a project, add hours to your work packages and watch the progress of each phase update. Free, no sign-up.
Open the app